This Western Federal Lands Highway Division project will replace the existing Dickey Creek bridge with a wider and longer structure that will safely provide access for all vehicles, bicyclists, and pedestrians, while reducing flood impacts and restoring natural river...
This Western Federal Lands Highway Division and National Park Service project replaced utilities in the Going to the Sun Road corridor between the Lake McDonald Lodge and Apgar Village within Glacier National Park, Montana. Specifically, this project included...
This Western Federal Lands Highway Division project resurfaced approximately 35 miles of roadway and parking areas in California’s Lassen Volcanic National Park. The proHNS Consultant Project Engineer (CPE) oversaw all aspects of construction — from asphalt...
This Western Federal Lands Highway Division project reconditioned and paved more than five miles of existing aggregate surfaced road, removed overgrown vegetation, installed drainage systems, constructed a Mechanically Stabilized Earth (MSE) wall, and installed...
proHNS provided a full construction inspection and contract administration team on AK DOT&PF’s Sawmill Creek Road project, which resurfaced the roadway and made pedestrian improvements between Lake Street and Jeff Davis Street. Our services included...
proHNS provided contract administration and inspection services for this downtown Juneau project that replaced the existing 8″ ductile iron water main with new 10″ HDPE water main, a new 10″ gate valve, and associated water services to nearby...
proHNS designed roadway and utility improvements to Misty Lane, a 320-foot stub street dead-ending in a cul-de-sac in North Douglas’ Bayview subdivision. Design elements included: 1) Full water system reconstruction with new 8” HDPE water main line, 1” poly water...
proHNS designed and inspected the renovation of this water booster pump station that supplies municipal water to Juneau’s Bonnie Brae Subdivision. The renovated station features two new 3-hp pumps and a new 30-hp pump to supply water during high demand periods...
This FAA-funded project addressed multiple safety concerns by resurfacing and rehabilitating the existing taxiways, aprons, and runways. It was one of the first projects in Alaska to bid with the new Standard Specifications for Airport Construction, which are based on...
proHNS is currently designing the reconstruction of several Haines Borough roadways and culverts that were severely damaged during a December 2020 storm event. Our scope of engineering services for this work includes providing surveying, civil-site, utility design,...
proHNS deftly designed this complicated utility and drainage improvement project, which will replace multiple underground water transmission and distribution pipe networks with new 10” and 14” HDPE pipe, water services, and hydrants. Work will also include...
Under our IDIQ with WFLHD, proHNS provided a Project Engineer for Phase II of this project that is repairing roadway sites damaged during a large storm event in 2016. The proHNS Project Engineer oversaw all aspects of construction to ensure the contractor executed...